The World's Largest Source of  Wireless Internet Information  Wireless Internet Products and Services Spacer E-mail this  page to a friend Print this  Page Make  My Favorite Homepage  Fixed Wireless Internet Equipment Spacer Log onto BWE Main Site Sign up to receive the  Newsletter
Turnkey  Solutions Using Wi-Fi Products and Services Example Wireless Internet City Graphic Turnkey  Wireless Internet Solutions Using Wi-Fi Products and Services Spacer
802.11a Wireless Internet Advertising Banner Spacer
 Wireless Internet HotSpots Using Wi-Fi Technology Spacer
 Wireless Internet Technology and Wi-Fi Companies Spacer  Home Page Home  Wireless Internet Alliance and HotSpot Companies Spacer  Site Map of Wireless Internet Links Site Map  Wireless Internet WiFi Sniffer and Antenna Spacer  Contact Us Contact Us  Wireless Internet Security and Hotspot Locations Spacer About About Fuel Cell News
Fuel Cell Wireless Internet Advertising Banner Spacer
How
to
Adver-
tise
TrangoLINK Giga - 6 GHz & 18 GHz Licensed Digital Microwave Wireless Backhaul System Check
Our
Stats
Fuel Cell Wireless Internet Advertising Banner Opportunity Spacer
Fuel Cell Wireless Internet Antennas and Transverters Fuel Cell Wireless Internet Radio, Bridges, Routers and Amplifiers Fuel Cell Wireless Internet CPE (Customer Premises Equipment) Fuel Cell Wireless Internet Towers and Antenna Mounts Fuel Cell WLANs (Wireles Local Area Networks)and HotSpot Access Points Fuel Cell Wireless Internet Test Equipment, Spectrum Analyzers and Sniffers Fuel Cell Wireless Internet Billing, Authentication, Security, Encryption and SNMP Network Management Software Products Fuel Cell Wireless Internet LMR Cabling, Connectors, and Rainproofing Kits
Fuel Cell Wireless Internet Technology, Standards, and Product Information Spacer
Fuel Cell fixed Wireless Internet networks spacer News Release for this Fuel Cell Wireless Internet Product or Service Contact Information for this Fuel Cell Wireless Internet Company Technical Specification Sheets for this Fuel Cell Wireless Internet Press Release Where To Buy the Fuel Cell Wireless Internet Products and Services Mentioned in this Release Print a Printer Friendly Copy of this Fuel Cell Press Release Send this Fuel Cell Wireless Internet Link to a Friend Click here to move to the next Fuel Cell Wireless Internet press release Fuel Cell Wireless Internet wifi test equipment border
 Wireless Internet wifi customer premises equipment border  Wireless Internet wlans border  Wireless Internet test equipment border
Fuel Cell Wireless Internet software border  Wireless Internet LMR cabling border
Renegy Provides Update on Snowflake Biomass Plant


02/14/08 - Renegy Holdings, Inc. announced that its Snowflake White Mountain Power biomass plant is on schedule to begin commercial operations during the second quarter of 2008. The remaining milestones to achieve commercial operation of the plant, and their target completion dates, are as follows:

-- First fire of boiler - February -- Steam turbine started - March -- Plant begins generating electrical power - May -- Full commercial operations - June

As the plant nears completion, Renegy currently expects that the final cost of the facility will exceed its original budget by approximately $12.5 million. Approximately half of this increase is attributable to cost overruns resulting from rising costs of labor, building materials and other construction challenges, while the remainder is attributable to new investments in the plant including a complete overhaul of the turbine, condenser and other used components, as well as new buildings and equipment added to the scope of the project over the past few months. As previously contemplated by the Contribution and Merger Agreement, Renegy will contribute $2.0 million toward the total amount of cost overruns. In addition, Renegy will pay for $6.0 million of the new capital investments described above that have been, or may be, incurred relating to the acquisition of new assets and other plant enhancements that are expected to further increase the efficiency, reliability and long-term operating performance of the plant. The balance of any costs in excess of the original budget will be paid by Renegy's Chairman and CEO Bob Worsley as outlined in the CMA.

Despite the amount of cost overruns and investment in plant upgrades as outlined above, the capital cost of the 24 megawatt plant, excluding financing and other soft costs, is currently expected to total $58.5 million, which remains below industry estimates of the cost to build a new biomass plant, which range from $2,500 to $3,000 per kilowatt. Furthermore, Renegy's $6.0 million investment in plant enhancements is expected to be substantially offset by a projected reduction in the costs expected to be necessary to refurbish and commission a recently acquired biomass facility in Susanville, California, resulting from its plans to maintain the plant at its current location. More information on the Company's Susanville plant can be found in a separate release issued.

"We are rapidly approaching some key milestones relating to the completion and commissioning of our Snowflake facility that should enable us to begin generating electrical power in the second quarter of this year," stated Bob Worsley. "While disappointed in the cost increases, I am pleased to report that we are on track to fire the boiler later this month and to complete a performance test of the entire plant during April. The additional investment we have elected to make is expected to improve the economics of the plant over the long-term by increasing its potential to achieve higher performance and greater availability, while at the same time reducing operating and maintenance costs. While our original cost projections have been impacted by a variety of internal and external forces, including a significant rise in the cost of building materials being generally experienced in national and global markets, we remain focused on completing the plant in both a timely and quality manner to meet the obligations under our financing, insurance and power purchase agreements."

Worsley continued, "In addition to the impending start-up of our first plant, we continue to be enthusiastic about the growth prospects for biomass energy and the many opportunities we have identified in the marketplace to acquire existing biomass to electricity facilities and related businesses that complement our current business activities."

As a result of the increased capital investment in the plant, combined with its growth objectives, Renegy may seek additional debt or equity financing in 2008 to fund the refurbishment of its Susanville biomass plant and other strategic opportunities, as well as for general corporate purposes. In the interim, to neutralize the impact of the $6.0 million of additional investment in the Snowflake plant, Bob Worsley has agreed to provide the Company with a $6.0 million revolving line of credit from which the Company may draw, if needed, for any near-term cash needs. In parallel, Bob Worsley has agreed to personally guarantee up to $6.0 million should the Company choose to pursue an alternate revolving line of credit with a financial institution. Access to either such credit line will allow Renegy to seek additional financing at a measured pace as growth opportunities arise. The Company is also continuing its search for the addition of a chief operating officer with significant power industry and plant construction experience to add depth to its management team and oversee the development and commissioning of future biomass power generating facilities.

In other news, it was announced Monday that AbitibiBowater ("Abitibi") has agreed to sell its Snowflake, Arizona newsprint mill, the site of Renegy's Snowflake biomass plant, to British Columbia-based Catalyst Paper Corp., a leading North American producer of mechanical printing papers. According to the announcement, Catalyst Paper intends to continue operating the Snowflake paper mill as a means to strengthen its competitive position and market share by having a greater presence on the west coast of North America. Renegy currently has a 25-year lease and operating agreement (including a 25-year option) in place with Abitibi associated with its Snowflake biomass plant. As part of these agreements, Abitibi will supply recycled paper sludge produced by the mill, which is estimated to make up approximately 50% by weight (25% by energy content) of the biomass fuel to be used by Renegy's Snowflake plant. All such agreements currently in place with Abitibi remain intact and are enforceable under the new ownership scenario.

Renegy is also announcing today that it has completed its determination of final transaction costs and working capital adjustments associated with the $9.6 million sale of its SCR-Tech subsidiary last November. As previously noted, current stockholders of Renegy will receive additional value through an increased percentage of ownership in Renegy common stock based on the net cash proceeds of the SCR-Tech sale, which have been calculated at $9.3 million. After expenses and working capital adjustments required under the CMA relating to the combination of the businesses of Catalytica Energy Systems and the renewable energy divisions of NZ Legacy, LLC last October, the final net effect is an approximate 1.5% reduction in Renegy common stock currently owned by the Worsley Trust. Accordingly, current stockholders of Renegy now own approximately 42.8% of the outstanding common stock of Renegy and the Worsley Trust approximately 57.2%.

Additional information relating to the Snowflake plant and risk factors can be found in a Form 8-K filed by the Company today with the Securities and Exchange Commission. The Company expects that any securities offered as part of any capital raising activities as described in this press release will not be registered under the Securities Act of 1933 and therefore may not be offered or sold in the United States absent registration or an applicable exemption from registration requirements. This press release shall not constitute an offer to sell or solicitation of an offer to buy securities and is issued pursuant to Rule 135c under the Securities Act of 1933.

Fuel Cell Wireless Internet Antennas and Transverters Spacer Fuel Cell Wireless Internet Radios, Bridges, Routers and Amplifiers Spacer
Fuel Cell Wireless Internet CPE (Customer Premises Equipment) Spacer Fuel Cell Wireless Internet Tower and Antenna Mount Spacer Fuel Cell WLAN (Wireless Local Area Network) and Wireless Internet HotSpot Access Points Spacer

Fuel Cell Wireless Internet Test Equipment, Spectrum Analyzers, and Network Sniffers
The Fuel Cell Wireless Internet Most Coveted Hot Products List - only $50 per week to list your product here!
www.fuel-cellnews.com

Get great advice from these leading edge Fuel Cell Wireless Internet discussion groups
Leading Newsletters on Fuel Cell, Fuel Cell, OFDM and Free Space Optics Wireless Internet Technology

Recent Fuel Cell Newsletters

Enter your email address for a FREE subscription.

Get great advice from these leading edge Fuel Cell Wireless Internet discussion groups
Fuel Cell Classified Ads for Used Equipment, Jobs, Contracts, Bids
802.16 Sister Wireless Internet Publications on 802.11a, 802.11b, 802.11g, 802.16, FSO, OFDM and Wi-Fi Spacer
Publications: Broadband Wireless Exchange Magazine BWE 802.11 News 802.11 802.11a News 802.11a 802.11b News 802.11b 802.11g News 802.11g 802.11 Information 802.11i 802.16 News 802.16 Bluetooth News Bluetooth Cable Modem News Cable Modems DSL Daily News DSL Free Space Optic(FSO) News Free Space Optics Fuel Cell/Solar Power News Fuel Cells/Solar Power Hotspot News Hotspots Orthogonal Frequency Division Multiplexing (OFDM) NewsOFDM Satellite Broadband Internet News Satellite Broadband Spectrum Resellers News Spectrum Resellers Wi-Fi Hotspot Zones News Wi-Fi

Corporate: About the Broadband Wireless Exchange Magazine bullet point About BWE Inc. How to Contact the Fuel Cell Staff bullet point Contact Fuel Cell News How to Send Corrections to the Fuel Cell Staff bullet point Corrections How to Advertise on the Fuel Cell web site bullet point How to Advertise Careers open for the Fuel Cell News web site bullet point Careers The Fuel Cell News Privacy Policy bullet point Privacy Policy

Copyright © 2000-2005 BWE, Inc. All Rights Reserved. Fuel Cell Wireless Internet business planning bullet point